Community Water System · PWSID NJ0612001

Bayshore Mobile Home Park

Serves 81 peopleGroundwaterOwner: PrivateStow Creek, New Jersey
1 open treatment violation.

Open for: Revised Total Coliform Rule. EPA counts treatment-technique violations as health-based: a required protective step was not done. It is not a measurement of contamination.

On record since 2005: 86 violations. 10 over the limit · 2 treatment lapses · 69 missed or late tests · 5 notices or reports. Most recent began 2025-03-06.

For this year's test results, ask the utility for its annual Consumer Confidence Report. Every community system must publish one.

10Over the limit
2Treatment lapse1 open
69Missed or late test
5Notice or report1 open

More violations on record than 98% of active water systems in New Jersey. Small systems with no staff chemist often rack up missed-test violations; big utilities rarely do.

The record, year by year

2005 · Notice or report: 2200520102015 · Over the limit: 52015 · Over the limit: 52015 · Missed or late test: 222015 · Missed or late test: 222015 · Missed or late test: 222015 · Missed or late test: 222015 · Missed or late test: 222015 · Missed or late test: 222015 · Missed or late test: 222015 · Missed or late test: 222015 · Notice or report: 120152016 · Over the limit: 52016 · Over the limit: 52016 · Missed or late test: 12017 · Missed or late test: 52017 · Missed or late test: 52018 · Treatment lapse: 12018 · Missed or late test: 62018 · Missed or late test: 62019 · Missed or late test: 120202021 · Missed or late test: 72021 · Missed or late test: 72021 · Missed or late test: 72021 · Notice or report: 12022 · Missed or late test: 42022 · Missed or late test: 42023 · Missed or late test: 52023 · Missed or late test: 52024 · Treatment lapse: 12024 · Missed or late test: 182024 · Missed or late test: 182024 · Missed or late test: 182024 · Missed or late test: 182024 · Missed or late test: 182024 · Missed or late test: 182025 · Notice or report: 12025
One square ≈ 3 violations (rounded up), by the year they began. Empty columns are years with nothing on EPA's record.
12% over the limit · 102% treatment lapse · 280% missed or late test · 696% notice or report · 5

Across New Jersey, 74% of violations are missed or late tests and 2% are water over a limit.

How far over the limit

at the limit2×5×10×100×+Gross Alpha, Excl. Radon and UCombined Radium (-226 and...Nitrate2016-07-01 · Gross Alpha, Excl. Radon and U: measured 19.00 PCI/L vs limit 15.00 PCI/L (1.3×)2016-04-01 · Gross Alpha, Excl. Radon and U: measured 33.00 PCI/L vs limit 15.00 PCI/L (2.2×)2016-04-01 · Combined Radium (-226 and -228): measured 9.00 PCI/L vs limit 5.00 PCI/L (1.8×)2016-01-01 · Combined Radium (-226 and -228): measured 10.00 PCI/L vs limit 5.00 PCI/L (2.0×)2016-01-01 · Gross Alpha, Excl. Radon and U: measured 36.00 PCI/L vs limit 15.00 PCI/L (2.4×)2015-10-01 · Gross Alpha, Excl. Radon and U: measured 32.57 PCI/L vs limit 15.00 PCI/L (2.2×)2015-10-01 · Combined Radium (-226 and -228): measured 9.50 PCI/L vs limit 5.00 PCI/L (1.9×)2015-10-01 · Nitrate: measured 13.35 MG/L vs limit 10.00 MG/L (1.3×)
Each dot is one over-the-limit violation: the measured value divided by the limit it broke, on a log scale. Most legal limits for chemicals are running averages set for a lifetime of drinking, so “just over” and “ten times over” are very different news. Hover a dot for the numbers.

What you can do

  • Total Coliform Bacteria: If your water system has coliform violations, consider boiling water or using bottled water until the system confirms the issue is resolved. Contact your water provider for their latest test results and any boil-water advisories.

Lead & copper at the tap

Utilities sample taps in homes most likely to have lead pipes, and report the 90th-percentile result: 9 in 10 homes sampled came in at or below this number. Above the red line (the action level) the utility must act. The action level is not a safe level; EPA's health goal for lead is zero. EPA's file does not date these results, so they are shown highest first.

Lead, 90th percentile 13 results on file · action level 15 ppb

11.9 ppb
6 ppb
5.5 ppb
4.7 ppb
2.9 ppb
2.4 ppb
2.2 ppb
2.1 ppb
2 ppb
1.1 ppb
0.9 ppb
0.6 ppb
0 ppb

Open now (2)

  1. 2025-03-06Public NoticePN Violation for NPDWR ViolationOpen
  2. 2024-12-24Revised Total Coliform RuleTTOpen

Every violation on record

  1. 2025-03-06Public NoticePN Violation for NPDWR ViolationOpen
  2. 2024-12-24Revised Total Coliform RuleTTOpen
  3. 2024-10-01Radium-228Monitoring, RegularBack in compliance
  4. 2024-10-01Radium-226Monitoring, RegularBack in compliance
  5. 2024-10-01Combined Radium (-226 and -228)Monitoring, RegularBack in compliance
  6. 2024-10-01Combined UraniumMonitoring, RegularBack in compliance
  7. 2024-10-01Gross Alpha, Excl. Radon and UMonitoring, RegularBack in compliance
  8. 2024-07-01SodiumMonitoring, RegularPeriod ended · no return to compliance on file
  9. 2024-07-01NitrateMonitoring, RegularBack in compliance
  10. 2024-07-01ChlorineMonitoring and Reporting (DBP)Back in compliance
  11. 2024-07-01Radium-228Monitoring, RegularBack in compliance
  12. 2024-07-01Radium-226Monitoring, RegularBack in compliance
  13. 2024-07-01Combined Radium (-226 and -228)Monitoring, RegularBack in compliance
  14. 2024-07-01Combined UraniumMonitoring, RegularBack in compliance
  15. 2024-07-01Gross Alpha, Excl. Radon and UMonitoring, RegularBack in compliance
  16. 2024-04-01Radium-228Monitoring, RegularBack in compliance
  17. 2024-04-01Radium-226Monitoring, RegularBack in compliance
  18. 2024-04-01Combined Radium (-226 and -228)Monitoring, RegularBack in compliance
  19. 2024-04-01Combined UraniumMonitoring, RegularBack in compliance
  20. 2024-04-01Gross Alpha, Excl. Radon and UMonitoring, RegularBack in compliance
  21. 2023-07-01Lead and Copper RuleWater Quality Parameter M/RBack in compliance
  22. 2023-01-01Combined Radium (-226 and -228)Monitoring, RegularBack in compliance
  23. 2023-01-01Combined UraniumMonitoring, RegularBack in compliance
  24. 2023-01-01Radium-226Monitoring, RegularBack in compliance
  25. 2023-01-01Gross Alpha, Excl. Radon and UMonitoring, RegularBack in compliance
Show the other 61 entries
  1. 2022-10-01Combined Radium (-226 and -228)Monitoring, RegularBack in compliance
  2. 2022-10-01Radium-226Monitoring, RegularBack in compliance
  3. 2022-10-01Radium-228Monitoring, RegularBack in compliance
  4. 2022-10-01Lead and Copper RuleFollow-up Or Routine LCR Tap M/RBack in compliance
  5. 2021-07-11Revised Total Coliform RuleRPTBack in compliance
  6. 2021-06-01Revised Total Coliform RuleMONBack in compliance
  7. 2021-04-01ChlorineMonitoring and Reporting (DBP)Back in compliance
  8. 2021-04-01Radium-228Monitoring, RegularBack in compliance
  9. 2021-04-01Radium-226Monitoring, RegularBack in compliance
  10. 2021-04-01Combined Radium (-226 and -228)Monitoring, RegularBack in compliance
  11. 2021-04-01Combined UraniumMonitoring, RegularBack in compliance
  12. 2021-04-01Gross Alpha, Excl. Radon and UMonitoring, RegularBack in compliance
  13. 2019-01-01Lead and Copper RuleWater Quality Parameter M/RBack in compliance
  14. 2018-10-01Radium-228Monitoring, RegularBack in compliance
  15. 2018-10-01Radium-226Monitoring, RegularBack in compliance
  16. 2018-10-01Combined Radium (-226 and -228)Monitoring, RegularBack in compliance
  17. 2018-10-01Combined UraniumMonitoring, RegularBack in compliance
  18. 2018-10-01Gross Alpha, Excl. Radon and UMonitoring, RegularBack in compliance
  19. 2018-07-01Lead and Copper RuleWQP Entry Point/Tap Treatment Technique Non-ComplianceBack in compliance
  20. 2018-01-01Lead and Copper RuleWater Quality Parameter M/RBack in compliance
  21. 2017-07-01Lead and Copper RuleWater Quality Parameter M/RBack in compliance
  22. 2017-01-01Lead and Copper RuleWater Quality Parameter M/RBack in compliance
  23. 2017-01-01Gross Alpha, Excl. Radon and UMonitoring, RegularBack in compliance
  24. 2017-01-01Combined Radium (-226 and -228)Monitoring, RegularBack in compliance
  25. 2017-01-01Combined UraniumMonitoring, RegularBack in compliance
  26. 2016-07-01Lead and Copper RuleWater Quality Parameter M/RBack in compliance
  27. 2016-07-01Gross Alpha, Excl. Radon and UMCL, Averagemeasured 19.00 PCI/L · limit 15.00 PCI/LBack in compliance
  28. 2016-04-01Gross Alpha, Excl. Radon and UMCL, Averagemeasured 33.00 PCI/L · limit 15.00 PCI/LBack in compliance
  29. 2016-04-01Combined Radium (-226 and -228)MCL, Averagemeasured 9.00 PCI/L · limit 5.00 PCI/LBack in compliance
  30. 2016-01-01Combined Radium (-226 and -228)MCL, Averagemeasured 10.00 PCI/L · limit 5.00 PCI/LBack in compliance
  31. 2016-01-01Gross Alpha, Excl. Radon and UMCL, Averagemeasured 36.00 PCI/L · limit 15.00 PCI/LBack in compliance
  32. 2015-11-28Public NoticePN Violation for NPDWR ViolationBack in compliance
  33. 2015-10-01Gross Alpha, Excl. Radon and UMCL, Averagemeasured 32.57 PCI/L · limit 15.00 PCI/LBack in compliance
  34. 2015-10-01Combined Radium (-226 and -228)MCL, Averagemeasured 9.50 PCI/L · limit 5.00 PCI/LBack in compliance
  35. 2015-10-01Combined UraniumMonitoring, RegularBack in compliance
  36. 2015-10-01NitrateMCL, Averagemeasured 13.35 MG/L · limit 10.00 MG/LBack in compliance
  37. 2015-07-01Gross Alpha, Excl. Radon and UMCL, Averagemeasured 19.27 PCI/LBack in compliance
  38. 2015-07-01Combined Radium (-226 and -228)MCL, Averagemeasured 9.72 PCI/LBack in compliance
  39. 2015-01-01StyreneMonitoring, RegularBack in compliance
  40. 2015-01-01EthylbenzeneMonitoring, RegularBack in compliance
  41. 2015-01-01TolueneMonitoring, RegularBack in compliance
  42. 2015-01-01BenzeneMonitoring, RegularBack in compliance
  43. 2015-01-01ChlorobenzeneMonitoring, RegularBack in compliance
  44. 2015-01-01TetrachloroethyleneMonitoring, RegularBack in compliance
  45. 2015-01-011,1,2-TrichloroethaneMonitoring, RegularBack in compliance
  46. 2015-01-01TrichloroethyleneMonitoring, RegularBack in compliance
  47. 2015-01-011,2-DichloropropaneMonitoring, RegularBack in compliance
  48. 2015-01-01Carbon tetrachlorideMonitoring, RegularBack in compliance
  49. 2015-01-011,1,1-TrichloroethaneMonitoring, RegularBack in compliance
  50. 2015-01-011,2-DichloroethaneMonitoring, RegularBack in compliance
  51. 2015-01-01trans-1,2-DichloroethyleneMonitoring, RegularBack in compliance
  52. 2015-01-011,1-DichloroethyleneMonitoring, RegularBack in compliance
  53. 2015-01-01Vinyl chlorideMonitoring, RegularBack in compliance
  54. 2015-01-01p-DichlorobenzeneMonitoring, RegularBack in compliance
  55. 2015-01-01o-DichlorobenzeneMonitoring, RegularBack in compliance
  56. 2015-01-01DichloromethaneMonitoring, RegularBack in compliance
  57. 2015-01-01Xylenes, TotalMonitoring, RegularBack in compliance
  58. 2015-01-01cis-1,2-DichloroethyleneMonitoring, RegularBack in compliance
  59. 2015-01-011,2,4-TrichlorobenzeneMonitoring, RegularBack in compliance
  60. 2005-10-01Public NoticePN Violation for NPDWR ViolationBack in compliance
  61. 2005-07-01Consumer Confidence RuleCCR Complete Failure to ReportBack in compliance

System details

Population served81
Service connections27
Water sourceGroundwater
System typeCommunity Water System
OwnerPrivate
StatusActive
CityStow Creek
EPA ZIP on file08302

Areas served

  • Cumberland County

Reading this record

Bayshore Mobile Home Park is a community water system that draws from groundwater and serves about 81 people in Stow Creek, New Jersey. Everything above comes from the EPA's Safe Drinking Water Information System (SDWIS), where states report every violation by every public water system.

Four kinds of violation. Only one is a measurement of the water: over the limit means a test came back above a legal maximum (an MCL). A treatment lapse means a required protective step was not done, such as disinfection, filtration, fixing a defect an inspector found, or filing a lead-pipe inventory. A missed or late test means a required test was skipped or never reported. That is the most common kind, and the most misread: it does not mean the water was bad, and it does not mean the water was fine. Notices and reports covers public notices and the annual Consumer Confidence Report.

Status. “Back in compliance” means the state recorded a return to compliance. “Period ended” means the violation's compliance period is over but no return to compliance was ever filed, which is common in older records. EPA's federal copy lags state records by months, so call the utility for anything current.